Syntax
DaysInMonth( nMonth, [lLeapYear] ) --> nDaysInMonthArguments
nMonth
lLeapYear
Example
PROCEDURE Main()
Check( 'DaysInMonth( 2 ) ', DaysInMonth( 2 ), 28 )
Check( 'DaysInMonth( 2, .T. ) ', DaysInMonth( 2, .T. ), 29 )
Check( 'DaysInMonth( 11 ) ', DaysInMonth( 11 ), 30 )
Check( 'DaysInMonth( 13 ) ', DaysInMonth( 13 ), 0 )
RETURN
STATIC PROCEDURE Check( cTitle, xResult, xExpected )
QOut( cTitle + IIF( xResult == xExpected, "OK", "ERROR" ) )
RETURNOutput
DaysInMonth( 2 ) OK
DaysInMonth( 2, .T. ) OK
DaysInMonth( 11 ) OK
DaysInMonth( 13 ) OK